< Back to all clusters
[BUSINESS] · Mozambique · 3 sources

started · updated

Mungari Administrative Post connected to Mozambique's national electricity grid

The Mungari Administrative Post in the Guro District of Manica Province has been connected to Mozambique's National Electricity Grid (REN). The project, completed on September 20, 2026, is expected to benefit approximately 1,000 new customers in its first phase.

Financed by the Government of Mozambique with an investment of approximately 100 million Meticais, the infrastructure works included the construction of 40 kilometers of 33 kV medium voltage lines, 10 kilometers of low voltage network, and the installation of 150 public streetlights. This expansion aims to improve local lighting and community security.

With this connection, five of the ten planned Administrative Posts in Manica Province are now linked to the REN as part of a 2025–2029 development plan. Nationally, 362 out of 419 Administrative Posts are now powered by the main grid or alternative sources provided by the Energy Fund (FUNAE), leaving 57 remaining to be electrified. This initiative is part of a broader national strategy by Electricidade de Moçambique (EDM) to achieve universal electricity access by 2030.

Entities

Electricidade de Moçambique · Fundo de Energia · Government of Mozambique · Manica Province · Mungari

Claims

What the coverage asserts, and how many sources carry each claim.

  • [● 3 SOURCES] The construction works were completed on September 20, 2026. cartamz.com
  • [● 3 SOURCES] The project included the construction of 40 kilometers of 33 kV medium voltage lines. cartamz.com
  • [● 3 SOURCES] The expansion is part of a goal to achieve universal electricity access by 2030. cartamz.com
  • [● 3 SOURCES] The project cost approximately 100 million Meticais and was fully funded by the Government of Mozambique. cartamz.com
  • [● 3 SOURCES] Approximately 1,000 new customers will benefit from this first phase of operation. cartamz.com
  • [● 3 SOURCES] Out of 419 existing Administrative Posts in Mozambique, 362 are now connected to the grid or alternative sources. cartamz.com
  • [● 3 SOURCES] The Mungari Administrative Post in Manica Province is now connected to the National Electricity Grid (REN). cartamz.com
  • [● 3 SOURCES] The works involved installing 10 kilometers of low voltage network and 150 public streetlights. cartamz.com