NextGrid Energy commissions 60 MW battery storage facility in Croatia
NextGrid Energy has commissioned BESS Sibenik, a standalone battery energy storage system located at the IMPOL-TLM industrial complex in Sibenik, Croatia. The facility features a capacity of 60 MW and 120 MWh, providing two hours of storage at full output using Tesla Megapack XL equipment.
The project, valued at approximately 60 million euros, is the first standalone battery system of this scale connected to the Croatian transmission grid. It is designed to provide automatic frequency restoration reserve (aFRR) services to the transmission system operator, HOPS, to help balance generation and consumption.
Funding for the project included 16.8 million euros in equity from the European Bank for Reconstruction and Development (EBRD), alongside investments from Raiffeisen pension funds and IE-Energy. The project also received support from the EU Modernisation Fund, with approximately 15 million euros in grants expected to be utilized due to construction costs falling below initial estimates.
Entities
BESS Sibenik · European Bank for Reconstruction and Development · HOPS · NextGrid Energy · Šibenik