started · updated
NorthMark Compute and Cloud revises water usage for South Carolina data center
NorthMark Compute and Cloud has updated its water usage projections for the $3 billion Valara Data Center project in Spartanburg County, South Carolina. The company now estimates the facility will require an average of 1.2 million gallons of water per day at full buildout, with a potential peak demand of 1.6 million gallons per day.
This revised figure is significantly higher than the previously communicated estimate of 459,000 gallons per day. The company stated that the initial figure was based on a Phase I wastewater survey and did not reflect the total projected demand. NorthMark Compute and Cloud noted that the updated figures were provided to Spartanburg Water in February 2026.
Spartanburg Water has indicated that the project’s total demand remains within its capacity and can be served without negatively impacting existing or future customers.
Entities
NorthMark Compute and Cloud · South Carolina · Spartanburg County · Spartanburg Water · Valara Data Center