Oracle Project Jupiter faces pipeline delay in New Mexico
Oracle’s Project Jupiter, a massive AI data center development in New Mexico valued at up to $165 billion, is facing potential setbacks due to a delay in its natural gas fuel supply. Energy Transfer’s Transwestern unit has pushed the expected in-service date for the Green Chile pipeline from August 15, 2026, to February 1, 2027.
The pipeline is intended to supply up to 400 million cubic feet of natural gas per day to power Bloom Energy fuel cells, which are expected to provide up to 2.45 gigawatts of capacity for the site. The delay follows repeated refusals by New Mexico State Land Commissioner Stephanie Garcia Richard to approve the pipeline route, citing concerns over the impact on state trust lands, water resources, and increased emissions.
Despite the pipeline delay, Oracle has stated that the project remains on schedule as of July 2026. The 1,400-acre campus has already generated approximately $80 million in tax revenue and employs over 2,700 workers. Oracle previously warned federal regulators that delays to the fuel supply could jeopardize the broader objectives of the project.
Entities
Bloom Energy · Energy Transfer · Oracle · Project Jupiter · Stephanie Garcia Richard
Claims
What the coverage asserts, and how many sources carry each claim.
- [● 3 SOURCES] Project Jupiter is a massive AI data center development in New Mexico with an estimated investment of up to $165 billion. oilprice.com · thenextweb.com
- [○ 1 SOURCE] Oracle confirmed that Project Jupiter remains on schedule as of July 16, 2026.
- [● 2 SOURCES] Oracle warned federal regulators that delays to the Green Chile pipeline could jeopardize Project Jupiter. oilprice.com · thenextweb.com
- [● 3 SOURCES] The project plans to utilize up to 2.45 gigawatts of power via Bloom Energy solid oxide fuel cells. oilprice.com · thenextweb.com
- [○ 1 SOURCE] The project has generated approximately $80 million in tax revenue as of late July 2026.
- [● 2 SOURCES] The Green Chile Project in-service date has been delayed from August 15, 2026, to February 1, 2027. oilprice.com · thenextweb.com
- [● 2 SOURCES] The Green Chile pipeline is designed to deliver up to 400 million cubic feet of natural gas per day. oilprice.com · thenextweb.com
- [○ 1 SOURCE] New Mexico State Land Commissioner Stephanie Garcia Richard has twice refused the pipeline route due to concerns over water use, emissions, and state land impact. thenextweb.com