Patras natural gas network expansion triggers road works
Enaon EDA is expanding the natural gas distribution network in Patras, with multiple work fronts active across the city. As of September 28, a new work site has opened on Georgiou Olympiou street, covering the section from the Ilia street intersection to Solomou street, with completion expected by October 10.
Other ongoing projects include work on Archiepiskopou Ierotheou street, from Smyrni to Solomou, which began on September 21 and is slated for completion by October 3. Additionally, construction is underway on Korinthou street between Zaimi and Norman, scheduled to finish by October 7. Following this, crews will move to the section from Norman to Kefallonias between October 8 and October 22.
Further scheduled interventions include work on March 25 street on October 3, specifically the section from Gounari to D. Votsi. These projects are part of a broader development program expected to continue through October 22. Drivers are advised to expect temporary traffic regulations, including restrictions and interruptions, and to follow temporary signage.
Entities
Claims
What the coverage asserts, and how many sources carry each claim.
- [● 3 SOURCES] Works on Archiepiskopou Ierotheou, from Smyrni to Solomou, started on September 21 and are expected to finish by October 3. dete.gr · www.thebest.gr · pelop.gr
- [● 3 SOURCES] Enaon EDA is managing the natural gas distribution network expansion in Patras. dete.gr · www.thebest.gr · pelop.gr
- [○ 1 SOURCE] Korinthou street works will move to the section from Norman to Kefallonias between October 8 and October 22. pelop.gr
- [○ 1 SOURCE] Works are scheduled for March 25 street on October 3, in the section from Gounari to D. Votsi. pelop.gr
- [● 3 SOURCES] Works on Korinthou street, from Zaimi to Norman, began on September 23 and are scheduled to end on October 7. dete.gr · www.thebest.gr · pelop.gr
- [● 3 SOURCES] The works involve temporary traffic regulations, including restrictions or interruptions to vehicle movement. dete.gr · www.thebest.gr · pelop.gr
- [● 3 SOURCES] The overall natural gas network development program in Patras extends until October 22. dete.gr · www.thebest.gr · pelop.gr
- [● 3 SOURCES] New works on Georgiou Olympiou street, from Ilia to Solomou, began on September 28 and are scheduled to last until October 10. dete.gr · www.thebest.gr · pelop.gr