Pisárecké tunnels in Brno face extended closure
The Pisárecké tunnels in Brno, which were scheduled to reopen this Saturday following a six-week reconstruction, will remain closed for at least an additional nine days. David Fiala, director of the Brno plant for the Road and Motorway Directorate (ŘSD), stated that the contractor, Eltodo, failed to complete the work within the contractual deadline.
Disputes have arisen between ŘSD and Eltodo regarding the installation of electricity meters required to connect the tunnels to the power grid and begin testing safety systems, including light signals, SOS messages, and fire systems. Eltodo's executive director, Petr Kovář, noted that testing can only commence once the connection is secured.
If the delay is proven to be the fault of the contractor, a penalty of one million CZK per day may apply. In addition to the tunnel closure, weekend traffic restrictions will also affect the D1 and D2 motorways near Brno due to bridge support construction, requiring drivers to use detour routes.
Entities
Brno · David Fiala · Eltodo · Petr Kovář · Ředitelství silnic a dálnic