Poland expands S19 expressway with new viaduct and tunnel projects
Significant infrastructure developments are underway for the S19 expressway in Poland. In Nienadówka, a new 156.4 meter long viaduct has successfully passed load testing. The tests, which involved ten 34-ton trucks, confirmed that the structure meets all design safety and stability requirements. This viaduct is part of a 14 kilometer expansion project intended to add a second carriageway, with completion expected by the end of 2026.
Additionally, construction approval has been granted for the Jawornik–Lutcza section of the S19. This 5.25 kilometer stretch, costing over 1.9 billion PLN, will feature an 815 meter viaduct and a 2,803 meter tunnel under Mount Kamieniec. The tunnel is expected to be the longest of three currently being built on the Podkarpackie S19 route. The project, managed by a Gülermak and Budimex consortium, is scheduled for completion in 2031.
Entities