[BUSINESS] · Poland · 26 sources

started · updated

S19 expressway: GDDKiA tenders 12.5 km section completion

The General Directorate for National Roads and Motorways (GDDKiA) has launched a tender to complete a 12.5-kilometer section of the S19 expressway between Domaradz and Krosno.

This move follows the termination of a contract with Mostostal Warszawa in May. The previous contractor was removed due to proposing design changes that were inconsistent with environmental decisions, as well as failing to respond to requests to resume work.

The new contract will follow a ‘design and build’ model. While the new contractor will not be starting from scratch, they will be responsible for preparing the necessary documentation to proceed with construction. The project is expected to take 29 months, excluding winter periods. The scope includes completing the road section, engineering structures, and developing traveler service areas in Zagórze, alongside pedestrian and bicycle infrastructure.

Entities

DK12 · DW297 · Domaradz · GDDKiA · Generalna Dyrekcja Dróg Krajowych i Autostrad · Krosno · Lower Silesian Road and Rail Service · Ministerstwo Infrastruktury · Mostostal Warszawa · S19 expressway

Claims

What the coverage asserts, and how many sources carry each claim.

  • [○ 1 SOURCE] The reconstruction of provincial road 785 in the Łódź region has a project value of 34.08 million PLN. filmowalodz.pl
  • [○ 1 SOURCE] The completion date for the DW297 project is scheduled for October 31, 2029, contingent on environmental decisions.
  • [○ 1 SOURCE] The new contractor for the S19 section will operate under a 'design and build' formula. bizblog.spidersweb.pl
  • [○ 1 SOURCE] GDDKiA terminated its contract with Mostostal Warszawa in May due to design changes inconsistent with environmental decisions. bizblog.spidersweb.pl
  • [○ 1 SOURCE] The General Directorate for National Roads and Motorways (GDDKiA) has announced a tender to complete a 12.5 km section of the S19 expressway. bizblog.spidersweb.pl
  • [○ 1 SOURCE] The financial and substantive progress of the DW297 reconstruction is approximately 6% of the contract value.