Polish nuclear plant construction advances as Bechtel takes site, Budimex begins earthworks

Polskie Elektrownie Jądrowe (PEJ) transferred the land for the first Polish nuclear power plant at Choczewo to U.S. contractor Bechtel, which will act as the general contractor and manage the site. Bechtel appointed Polish construction firm Budimex to carry out earthworks and site‑preparation tasks, including terrain leveling, temporary roads, drainage and erosion control. The contract for the earthworks is valued at roughly 208.9 million PLN (about 49 million EUR). Over 330 ha of forested land have been cleared and prepared for the project. The plant will consist of three Westinghouse AP1000 reactors with a combined capacity of about 3.75 GW, with the first concrete pour scheduled for 2028 and commercial operation of the first block expected in 2036. The development is described by officials as the largest investment in Poland’s modern economy and a strategic step toward energy security and diversification away from coal.

Entities: Artur Popko · Bechtel · Budimex · Marek Woszczyk · Miłosz Motyka · Polskie Elektrownie Jądrowe · Polskie Elektrownie Jądrowe (PEJ)

Claims

What the coverage asserts, and how well corroborated each claim is across sources.

  • [● 7 SOURCES] Budimex signed a contract to perform earthworks and site‑preparation for the plant. (Budimex press release)
  • [● 3 SOURCES] First concrete pour is scheduled for 2028 and the first block is expected to start commercial operation in 2036. (PEJ timeline)
  • [● 4 SOURCES] The plant will consist of three Westinghouse AP1000 reactors with a total capacity of about 3.75 GW. (Project description)
  • [● 2 SOURCES] The earthworks contract is valued at about 208.9 million PLN (≈ 49 million EUR). (Budimex announcement)
  • [● 3 SOURCES] Bechtel will act as the general contractor and manage the nuclear plant site. (PEJ statements)
  • [● 5 SOURCES] Polskie Elektrownie Jądrowe transferred the land for the first Polish nuclear power plant at Choczewo to Bechtel. (PEJ press release)
  • [● 4 SOURCES] Over 330 ha of forested land have been cleared and prepared for the project. (PEJ statements)