Polish Supreme Court rules on transmission easement compensation

The Supreme Court of Poland has confirmed that compensation for transmission easements can include losses incurred beyond the immediate installation strip. In a specific case involving a high-pressure gas pipeline, the court upheld a 186,000 PLN payment to landowners.

The ruling clarifies that remuneration should account for restrictions within the so-called ‘controlled zone’ required for the safe operation and maintenance of the infrastructure. This decision follows a significant Constitutional Tribunal ruling from December 2025, which has increased interest among landowners regarding compensation for land impacted by utility infrastructure.