Porthos CO2 storage project faces 397 million euro delay

The Porthos CO2 storage project in the Netherlands is facing delays and cost increases totaling up to 397 million euros, according to Minister Stientje van Veldhoven and State Secretary Jo-Annes de Bat.

While the facility was intended to open by the end of 2027, officials noted that a 2028 opening is a more realistic timeline. The cost increase is primarily attributed to technical setbacks and additional work required for the offshore platform and the compressor station, which account for an estimated 361 million euros of the total rise.

Porthos is a joint venture between the Port of Rotterdam Authority, Gasunie, and Energie Beheer Nederland (EBN). While the first two partners can cover their cost increases from their own balance sheets, EBN has requested financial support from the Ministry of Economic Affairs. Clarity on this request is expected in next year’s spring memorandum.

The project aims to capture CO2 from Rotterdam industry and store it in depleted gas fields beneath the North Sea, representing the world’s first large-scale project of its kind to support climate targets.

Entities

Energie Beheer Nederland · Gasunie · Port of Rotterdam Authority · Porthos · Stientje van Veldhoven