Rio Riazzone bridge safety works approved in Scandiano

The municipalities of Scandiano and Casalgrande have approved safety works for the Rio Riazzone bridge, a key connection on the provincial road serving the local ceramic district. The project, valued at 180,000 euros, is a joint effort between the two administrations.

Scandiano will fund 75% of the costs, while Casalgrande will cover the remaining 25%, following an agreement established in 2019. The technical intervention includes repairing the concrete beam covers and waterproofing the bridge deck, followed by resurfacing the road.

Construction is scheduled to begin next week and is expected to last approximately 60 days, depending on weather conditions. To maintain traffic flow, the site will implement alternating one-way lanes regulated by a traffic light system. Officials stated that no complete closure of the road is expected during the works.

Entities

Enrico Baschieri · Lorenzo Giordani · Municipality of Casalgrande · Municipality of Scandiano · Rio Riazzone

Claims

What the coverage asserts, and how many sources carry each claim.

  • [● 3 SOURCES] Traffic will be managed via alternating one-way lanes controlled by traffic lights. www.modena2000.it
  • [● 3 SOURCES] The project includes repairing concrete beam cover and waterproofing the bridge deck. www.modena2000.it
  • [● 3 SOURCES] Construction is scheduled to begin next week. www.modena2000.it
  • [● 3 SOURCES] The total cost of the bridge intervention is 180,000 euros. www.modena2000.it
  • [● 3 SOURCES] The works are expected to last 60 days, weather permitting. www.modena2000.it
  • [● 3 SOURCES] The Municipality of Casalgrande will cover 25% of the costs. www.modena2000.it
  • [● 3 SOURCES] The Municipality of Scandiano will cover 75% of the costs. www.modena2000.it
  • [● 3 SOURCES] The bridge work is part of a three-year public works plan. www.modena2000.it