started · updated
Rostock lifting road closures after shipyard crane secured
Authorities in Rostock have completed stabilization work on the historic Helling crane, located at the former Neptunwerft site. Following the discovery of cracks and deformations in the crane's drawbar, nearby residential and commercial buildings were evacuated due to the risk of the jib collapsing.
Experts determined the damage was likely caused by rust and water freezing inside the drawbar component. The damaged part was replaced with a cable system, a structural change approved by monument preservation authorities.
Most road closures are being lifted, and residents have already returned to their homes. The historic 1976 structure, which is also used as a wedding venue, is expected to be available for events again once the remaining work area behind the shopping center is cleared.