Sagamore Bridge replacement secures $956 million in federal funding

Massachusetts officials have reached a major milestone in the replacement of the Sagamore Bridge, securing $956 million in federal grant funding. The state has also issued a Request for Proposals (RFP) for the project’s design-build contract, marking the final procurement phase before construction begins.

MassDOT expects construction to commence in winter 2027, with final proposals due in May 2027 and a public bid opening in July 2027. The Federal Highway Administration is anticipated to authorize an additional $371 million in federal funding in mid-October. The project, estimated to cost over $1.6 billion, will be managed by MassDOT in partnership with the Federal Highway Administration and the U.S. Army Corps of Engineers.

The RFP includes a requirement for the selected firm to enter into a project labor agreement (PLA) with specific local unions. While state officials defend the necessity of the agreement, a study from the Massachusetts Fiscal Alliance suggested that such an agreement could potentially increase project costs by $293 million.

The new infrastructure project aims to replace the 91-year-old bridge to improve safety and traffic flow for Cape Cod residents and visitors. The new eastbound span is projected to open in 2033.

Entities

Federal Highway Administration · MassDOT · Maura Healey · Sagamore Bridge · U.S. Army Corps of Engineers

Claims

What the coverage asserts, and how many sources carry each claim.

  • [● 2 SOURCES] The Federal Highway Administration is expected to authorize an additional $371 million in federal grant funding in mid-October. www.infohaiti.net · www.boston.com
  • [○ 1 SOURCE] The new eastbound span of the Sagamore Bridge is expected to open in 2033. www.boston.com
  • [○ 1 SOURCE] The winning design-build firm must execute a project labor agreement (PLA) with specific local unions. bankerandtradesman.com
  • [● 2 SOURCES] Construction on the Sagamore Bridge replacement project is expected to begin in winter 2027. bankerandtradesman.com · www.boston.com
  • [● 2 SOURCES] MassDOT expects final proposals for the design-build contract to be submitted in May 2027. www.infohaiti.net · www.boston.com
  • [○ 1 SOURCE] A study by the Massachusetts Fiscal Alliance estimated that a project labor agreement could increase costs by $293 million. bankerandtradesman.com
  • [● 3 SOURCES] The state has secured authorization for $956 million in federal grant funding for the Sagamore Bridge replacement. www.infohaiti.net · bankerandtradesman.com · www.boston.com
  • [○ 1 SOURCE] The preliminary project cost is estimated to total more than $1.6 billion. bankerandtradesman.com