Sibiu–Pitești Highway construction progresses on Robești and Balota tunnels
Construction continues on the Robești and Balota tunnels within Section 2 (Boița–Cornetu) of the A1 Sibiu–Pitești Highway. According to the Regional Directorate of Roads and Bridges (DRDP) Craiova, excavation for both galleries at the Robești Tunnel has been completed. Current efforts at this site focus on waterproofing and interior lining, with the right gallery reaching approximately 50% completion for interior lining.
Progress at the Balota Tunnel differs, as excavations are still ongoing. In the Balota Tunnel, excavation is at roughly 12% for the left gallery and 83% for the right gallery. These figures specifically refer to the galleries on the Sibiu–Pitești direction.
The development of these tunnels is subject to local geological conditions and required technical solutions. Section 2 and Section 3 of the A1 highway will traverse the Carpathian Mountains, aiming to ensure continuous traffic on Pan-European Corridor 4, which connects Constanța to Nădlac.
Entities
A1 Sibiu–Pitești Highway · Balota Tunnel · DRDP Craiova · Pan-European Corridor 4 · Robești Tunnel