Spanish authorities investigate AVE high-speed rail contract
The Central Operative Unit (UCO) of the Civil Guard is investigating potential irregular influence regarding the second adjudication of the San Rafael-Cuarto de la Jara section of the Madrid-Extremadura high-speed rail line.
The 8.8-kilometer stretch near Mérida was initially awarded in 2014 for 18 million euros to a subsidiary of the ACS group, but works failed to commence due to land availability issues and subsequent legal disputes with Adif.
A revised project was approved in July 2018, leading to a new tender process. Investigators are now examining communications from late 2018, specifically looking into whether the then-president of Adif, Isabel Pardo de Vera, informed Koldo García about upcoming tenders, including this rail project.
Entities
Adif · Isabel Pardo de Vera · Koldo García · Mérida · UCO