started · updated
Spanish gas power plants hit record low availability
Combined cycle gas plants in the Spanish peninsula have reached a historic low in availability, dropping to an average of 60.2% last month. This figure is significantly below the ten-year October average of 77.84% and the annual average of 82.3%.
Data from consultancy Revenergetica indicates that most of these outages were unplanned or forced due to equipment wear, imminent technical issues, or breakdowns. This instability follows the April 2025 blackout, which led Red Eléctrica de España (REE) to implement reinforced operations to maintain system voltage using reactive power.
The current situation adds tension to the electrical system amid ongoing disputes between REE and major energy companies regarding responsibility for previous energy shortages.