started · updated
Sports facility upgrades progress in Banja Luka and Podgorica
Infrastructure projects at two regional sports facilities have reached critical stages. At the Čaire stadium, home to BSK Banja Luka, the installation of the complete grass pitch is expected to be finished within 15 days. BSK Director Aleksandar Mićić stated that once the pitch and perimeter fencing are in place, the club will begin a second phase involving the construction of a new stand and changing rooms, a project valued at approximately 1.2 million KM.
In Podgorica, the roof renovation of the SC Morača sports center is complete. The project, valued at nearly 937,000 euros, will undergo functional testing to ensure its effectiveness. Miljan Ivanović, director of the managing company, noted that officials are waiting for autumn rainfall to verify the waterproofing, though they may simulate rain with emergency services if necessary. The renovation aims to resolve long-standing leakage issues that have persisted for years.
Entities
Aleksandar Mićić · BSK Banja Luka · Miljan Ivanović · Podgorica · SC Morača