Taiwan road closures scheduled for Wanda Line construction

Planned road closures and construction activities are scheduled for several major routes in Taiwan to facilitate infrastructure improvements.

For the Wanda Line CQ810 electrical engineering project, partial closures of the Provincial Highway 64 (Tai 64) will occur in stages. From September 29 to September 30, the westbound section between km 25 and km 28.4 will be closed. From October 1 to October 15, the eastbound section between km 25 and km 28.4 will be closed. These closures will take place nightly from 11:00 PM to 6:00 AM, excluding holidays and the National Day transport period from October 8 to October 11. The work involves high-voltage cable laying near Jing'an and Jingping stations.

Entities

New Taipei City Government · Taiwan · Wanda Line