started · updated
Lombardy allocates 1.55 million euros for Crema-Lodi cycling path
The Lombardy Regional Council has approved a resolution to allocate 1.55 million euros for the construction of a new section of a cycling path connecting Crema and Lodi. The project, promoted by Transport and Sustainable Mobility Councilor Franco Lucente, will be built along Provincial Road 235.
The infrastructure will link the territory of Bagnolo Cremasco, starting from the Morti delle Tre Bocche area, with the municipality of Crema near the Ombriano district. This development represents the first operational lot on the Cremasco side of the artery, following the completion of works in the Lodi province.
The Municipality of Crema will be responsible for the design and construction management. The delivery of this pedestrian and cycling section is scheduled to be completed by the end of 2027.
Entities
Alessandria · Anas · Asti · CIG Alpi del Sud · CISL Toscana Nord · Crema · Damiano Tommasi · Franco Lucente · Limone Piemonte · Lodi · Lucca · Regione Lombardia
Claims
What the coverage asserts, and how many sources carry each claim.
- [○ 1 SOURCE] Upon reopening, initial traffic will be restricted to alternating one-way flow between 6:00 and 23:00. www.cuneodice.it
- [○ 1 SOURCE] The Tenda tunnel is undergoing a total closure for six weeks starting Monday, September 21, 2026. www.cuneodice.it
- [○ 1 SOURCE] The long-term goal is to achieve full reopening without time-restricted transit windows. www.cuneodice.it
- [○ 1 SOURCE] The tunnel is scheduled to reopen on October 30, 2026. www.cuneodice.it
- [○ 1 SOURCE] The total closure of the Tenda tunnel was moved forward following a decision by CIG Alpi del Sud. www.cuneodice.it
- [○ 1 SOURCE] Works include maintenance at the French-side entrance and extraordinary maintenance of the tunnel. www.cuneodice.it