Lao Cai - Hanoi - Hai Phong railway project faces site clearance delays
The Ministry of Construction has reported significant delays in site clearance and public investment fund disbursement for the Lao Cai - Hanoi - Hai Phong railway project. The large-scale project involves the planned recovery of approximately 2,529.58 hectares of land across six provinces and cities.
As of the latest report, only 515.01 hectares (20.36%) have been recovered, with only 131 hectares (5.18%) officially handed over. While Hung Yen province has achieved a 99.05% recovery rate, other regions such as Hai Phong, Lao Cai, Phu Tho, Bac Ninh, and Hanoi report much lower progress in land handover.
Furthermore, the disbursement of the 2026 public investment plan for site clearance is currently low, with only 1,999 billion VND disbursed out of the allocated 13,847 billion VND, representing 14.43%. The Ministry has requested that local authorities ensure site clearance for agricultural, forestry, and public land is completed by December 31, 2026, with residential areas and technical infrastructure relocation to be finalized by June 30, 2027.
Entities
Asia Era One · Charoen Pokphand Group · Chula Sukmanop · Lao Cai - Hanoi - Hai Phong railway project · Ministry of Construction · State Railway of Thailand · Thailand · Vietnam