Tran Hung Dao Bridge construction in Hanoi reaches 52% completion
Construction of the Tran Hung Dao Bridge, a key transport project in Hanoi, has reached over 52% completion after one year of work. The project, which began on October 9, 2025, has a total investment of approximately 15,967 billion VND.
The bridge spans more than 4.1km, with the main section crossing the Red River measuring over 800m. It connects the intersection of Tran Hung Dao, Tran Thanh Tong, and Le Thanh Tong streets to Nguyen Son street in the Long Bien and Bo De wards.
As of late October 2026, contractors have completed 128 bored piles and 7 pier bases. The project has transitioned into the steel structure construction phase, with approximately 26,275 tons of steel being processed for the site. Currently, the construction site maintains 28 work fronts involving roughly 700 personnel and over 120 specialized machines and pieces of equipment.