Transport for NSW reaches milestone on Convicts Bridge project

Construction to reinstate Mitchells Causeway on the Great Western Highway has reached a significant milestone. More than half of the permanent piles required to support the future Convicts Bridge structure are now complete.

Transport for NSW confirmed that 900mm-wide piles are being drilled into sandstone bedrock. To accelerate the program, a second piling rig has been deployed to work alongside the current contractor. The project has also finished all necessary micropiling to allow access for major equipment.

In addition to the bridge work, crews are performing safety upgrades along Victoria Pass. These improvements include work on two westbound safety ramps and the replacement of roadside verges to enhance surface drainage. The goal is to have the road open to traffic by June 2027.