Trepça mine: 63 miners rescued after electrical failure in Stan Tërg
A power failure at the Trepça mine in Stan Tërg left 63 miners trapped underground for approximately eight hours. The incident occurred around 19:30 on October 7, 2026, caused by a malfunction in a 35 kV transformer in the first tunnel.
According to Trepça enterprise, 54 miners successfully evacuated using emergency stairs, while the remaining nine miners stayed underground until power was restored at 02:30. All miners were reported to be in stable health, though one miner reportedly suffered a leg injury during the incident.
The miners' union, led by Ibrahim Januzi, has criticized the incident as a serious safety alarm, citing outdated equipment and a lack of investment in infrastructure and alternative power supplies. The union is calling for an urgent assessment of safety systems and emergency routes.
The Institute for Research and Human Rights (IHDNj) has called for a full and independent investigation by the Prosecutor's Office to determine if there was institutional negligence or violations of safety regulations.
Entities
Artane Rizvanoli · Artane Rizvanolli · Ibrahim Januzi · Institute for Research and Human Rights · Stan Tërg · Stantërg · Trepça · Trepča
Claims
What the coverage asserts, and how many sources carry each claim.
- [● 2 SOURCES] A malfunction in the 35 kV system at the Tunnel Transformer caused a power outage at approximately 19:30. atvlive.tv · www.mesazhi.com
- [● 5 SOURCES] The health condition of the miners was reported as stable. tocka.com.mk · www.072info.com · www.espreso.co.rs · face.ba
- [● 2 SOURCES] 63 miners were present in the mine when the power failure occurred. atvlive.tv · www.mesazhi.com
- [● 2 SOURCES] The Institute for Research and Human Rights called for a full investigation into safety violations or negligence. informim.net
- [● 2 SOURCES] 54 miners evacuated via emergency stairs, while 9 miners waited for power to be restored. atvlive.tv · www.mesazhi.com
- [● 4 SOURCES] The miners' union cited a lack of investment and outdated equipment as recurring issues. tocka.com.mk · www.espreso.co.rs · face.ba
- [● 2 SOURCES] Electricity supply was restored at 02:30. atvlive.tv · www.mesazhi.com
- [● 2 SOURCES] The repair process was hindered by a lack of spare parts in stock. atvlive.tv · www.mesazhi.com