Ugljevik Thermal Power Plant suspends work due to coal shortage
The Ugljevik Thermal Power Plant (RiTE Ugljevik) has suspended electricity production due to a critical shortage of coal. Director Žarko Novaković reported that the Istok 1 mine is only providing 2,000 to 3,000 tons of coal daily, falling significantly short of the 8,000 tons required for continuous operation.
In addition to the fuel shortage, the facility faces severe financial and operational hurdles. The company is dealing with blocked bank accounts and a deepening financial crisis. To mitigate the impact on workers, the Government of Republika Srpska has approved a delay in tax payments to ensure employees can maintain health insurance coverage.
Operational recovery is further hindered by stalled work at the Istok 2 mine, caused by unresolved property-legal issues and a lack of machinery. While the government has promised 17 million KM for recapitalization, the full amount has not yet been received. Analysts warn that these production failures, combined with low hydropower output, will force the region to import electricity, increasing pressure on the local energy system.
Entities
Elektroprivreda Republike Srpske · Ivan Kopričica · Republika Srpska · RiTE Ugljevik · Žarko Novaković
Claims
What the coverage asserts, and how many sources carry each claim.
- [● 4 SOURCES] Unresolved property-legal relations and insufficient machinery are stalling work at the Istok 2 mine. www.zvornikdanas.com · 6yka.com · www.biznisinfo.ba · sarajevotimes.com
- [○ 1 SOURCE] The government approved a delay in tax payments for RiTE Ugljevik to allow workers to maintain health insurance. 6yka.com
- [● 2 SOURCES] The government promised 17 million KM for recapitalization, but funds are still largely awaited. www.zvornikdanas.com · www.biznisinfo.ba
- [○ 1 SOURCE] Energy analyst Zoran Pavlović warned that production problems in the sector will ultimately affect citizens. sarajevotimes.com
- [○ 1 SOURCE] Electricity market prices have reached nearly 200 euros per megawatt hour. sarajevotimes.com
- [● 2 SOURCES] The company is facing blocked bank accounts and a financial crisis. 6yka.com · sarajevotimes.com
- [● 2 SOURCES] The Istok 1 mine provides 2,000 to 3,000 tons of coal daily, while the plant requires approximately 8,000 tons. www.zvornikdanas.com · www.biznisinfo.ba
- [● 3 SOURCES] RiTE Ugljevik director Žarko Novaković stated the plant is suspending operations due to a coal shortage. www.zvornikdanas.com · 6yka.com · www.biznisinfo.ba