The House of Commons Public Accounts Committee (PAC) has issued a report criticizing the financing structure of the Sizewell C nuclear project, describing it as a ‘terrible deal for the UK taxpayer’. The committee expressed concern that under the regulated asset base model, consumers may bear the brunt of cost increases through higher electricity bills, while private investors face minimal capital risk despite expecting annual returns exceeding 10 per cent.
Estimates suggest that if construction costs reach a higher threshold of approximately £47.7 billion, consumers could face costs totaling nearly £22 billion, whereas investors might only contribute an additional £30 million. The PAC also noted that taxpayers remain liable for any shortfalls in decommissioning funding.
In addition to financial concerns, MPs are pressing the Government to ensure the project meets its pledge to spend 70 per cent of construction expenditure within the UK to support local jobs and supply chains. The committee has requested that the Department for Energy Security and Net Zero provide progress reports to Parliament every six months—rather than annually—covering costs, milestones, timetable changes, and the impact on electricity bills.
Entities
Department for Energy Security and Net Zero · EDF · National Wealth Fund · Public Accounts Committee · Sizewell C