Ulsan relocates tram depot to reduce construction delays

Ulsan Metropolitan City has announced plans to relocate the depot for its Urban Railway Line 1 (tram) from Taehwagang Station Plaza to a site south of the Ulsan Science Museum in Ok-dong.

The decision follows assessments that the original site, spanning approximately 23,595 square meters, sits on soft ground with an average depth of 24 meters. Relocating underground high-pressure gas pipes and improving the soil would have required at least six years of work. The new site features rocky ground that requires no additional soil improvement, allowing for construction to be completed in approximately 27 months.

While the depot construction time is reduced, the overall project timeline has been extended by two years to 2030 to accommodate administrative procedures, including design and environmental impact assessments. The total project cost is expected to increase by approximately 1.03 billion won, bringing the total to 382.47 billion won. The route length will be slightly reduced by 92 meters, though the 15 planned stations will remain.

Entities

Ok-dong · Taehwagang Station · Ulsan Metropolitan City · Ulsan Science Museum