Vietnam expressway projects face land clearance and material shortages
Several major expressway projects in Vietnam are encountering delays due to land clearance issues and shortages of construction materials.
The Ho Chi Minh City - My Thuan expressway expansion requires the clearance of over 117 hectares of land. While some areas in Ho Chi Minh City and Tay Ninh province have seen progress in land recovery notices, delays in relocating technical infrastructure such as electricity and telecommunications threaten to halt construction at several sites by late 2026.
Similarly, the My Thuan - Can Tho expressway project is facing difficulties with incomplete land handover in Vinh Long and Dong Thap provinces, alongside a scarcity of sand and stone. Specific obstacles include the relocation of 220kV power lines and water pipelines.
In the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway project, approximately 95.37% of the required land area has been handed over. However, challenges remain regarding the final relocation of assets and compensation payments for some remaining cases. Authorities aim to complete the remaining land handovers by November 2026 to ensure synchronized construction.
Entities
Ho Chi Minh City Transport Department · My Thuan Project Management Board · Saigon - My Thuan Expressway Co., Ltd. · Vietnam
Claims
What the coverage asserts, and how many sources carry each claim.
- [○ 1 SOURCE] Authorities aim to complete the remaining land handovers for the Ho Chi Minh City - Thu Dau Mot - Chon Thanh project by November 2026. thanhnien.vn
- [○ 1 SOURCE] The Ho Chi Minh City - Thu Dau Mot - Chon Thanh project requires the recovery of approximately 332.92 hectares of land. thanhnien.vn
- [○ 1 SOURCE] The My Thuan - Can Tho expressway project has reached 68% of its contract value for supplementary items. baoxaydung.vn
- [○ 1 SOURCE] Construction at certain sites of the Ho Chi Minh City - My Thuan expressway risks stopping by late October 2026 due to lack of land. baoxaydung.vn
- [○ 1 SOURCE] The My Thuan - Can Tho project is facing shortages of sand and stone materials. baoxaydung.vn
- [○ 1 SOURCE] The Ho Chi Minh City - My Thuan expressway expansion requires over 117 hectares of land clearance. baoxaydung.vn
- [○ 1 SOURCE] Over 95% of the land area for the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway has been handed over. thanhnien.vn