Vietnam infrastructure projects face material shortages and delays
Vietnam's major infrastructure and expressway projects are facing significant delays due to critical shortages of construction materials and ongoing land clearance issues. In the north, several expressway projects, including the Ninh Binh - Hai Phong and Hanoi Capital Ring Road 4 segments, are struggling with massive deficits of sand, soil, and stone. The Ministry of Construction has highlighted that these shortages threaten completion timelines for projects planned through 2026.
In the Mekong Delta and Ho Chi Minh City, the supply of sand and stone remains a major bottleneck. Reports indicate that Ho Chi Minh City faces a potential shortage of over 14 million cubic meters of construction sand. In response, Deputy Prime Minister Pham Gia Tuc has directed provinces to proactively secure material mine reserves for long-term projects spanning 2030-2045 to prevent future supply gaps.
Additionally, localized projects are also stalling. A critical landslide remediation project in Hoa Binh is behind schedule, with the contractor, Hoang Son Construction Investment Energy Trade JSC, citing financial difficulties as the reason for failing to begin work on cleared land.
Entities
Hoang Son Construction Investment Energy Trade JSC · Ministry of Construction · Pham Gia Túc · Vietnam
Claims
What the coverage asserts, and how many sources carry each claim.
- [○ 1 SOURCE] Hoang Son Construction Investment Energy Trade JSC admitted responsibility for delays in the Hoa Binh landslide remediation project due to financial difficulties. baophutho.vn
- [○ 1 SOURCE] The Cho Moi - Bac Kan expressway is facing difficulties regarding construction stone sources. baoxaydung.vn
- [○ 1 SOURCE] Several northern expressway projects face shortages of millions of cubic meters of soil and sand. baoxaydung.vn
- [○ 1 SOURCE] The Ninh Binh - Hai Phong expressway segment through Ninh Binh and Hung Yen lacks over 9 million cubic meters of filling sand. baoxaydung.vn
- [○ 1 SOURCE] Deputy Prime Minister Pham Gia Tuc requested provinces and cities to proactively prepare construction material mine funds for the 2030-2045 period. thuonghieusanpham.vn
- [○ 1 SOURCE] Component 3 of the Hanoi Capital Ring Road 4 project lacks approximately 4.3 million cubic meters of filling soil and nearly 4 million cubic meters of filling sand. baoxaydung.vn
- [○ 1 SOURCE] Ho Chi Minh City faces a risk of lacking 4 million cubic meters of stone and 14.34 million cubic meters of construction sand in 2026. thuonghieusanpham.vn
- [○ 1 SOURCE] As of July 2026, Mekong Delta projects lack over 6 million cubic meters of stone, 1.8 million cubic meters of construction sand, and nearly 30 million cubic meters of filling sand. thuonghieusanpham.vn