API
< Back to all clusters
[POLITICS] · Spain · 4 sources

started · updated

Villamayor closes municipal fronton for floor renovation

The Villamayor City Council has announced the temporary closure of the municipal fronton court located next to the swimming pools to begin floor rehabilitation works. The project involves an investment of 48,053.94 euros.

The renovation focuses on replacing approximately 297 square meters of the floor surface that exhibited cracks, unevenness, and sinking. The structural work includes the complete removal of damaged pavement, ground sanitation and compaction, the installation of a gravel base, and the execution of a 15-centimeter thick concrete slab to level the surface. The project also includes a full renewal of the finish and enclosure.

Works are expected to last approximately two months, depending on weather conditions. The council opted to postpone the intervention until autumn to avoid interfering with the summer bathing season and the high influx of visitors to the complex.

Entities

Salvador Ruano Sánchez · Villamayor City Council