World Bank warns Kenya of rising costs for Isiolo-Mandera Highway
The World Bank has issued a warning to the Kenyan government regarding compensation delays for the 740-kilometre Isiolo-Mandera Highway, part of the Horn of Africa Gateway Development Project. According to a letter from World Bank Division Director Qimiao Fan, delays in providing contractors with unrestricted land access are disrupting construction timelines and risking significant cost overruns.
The Bank estimates that every additional month of delay exposes the project to approximately KSh1.2 billion in extra costs. These expenses include supervision, security, site facilities, idle equipment, personnel, price escalation, and equipment demobilization and remobilization costs.
While compensation funds have been available since 2024, the process reportedly only began in November 2025 and has been limited to the Isiolo-Modogashe section. The World Bank has committed approximately KSh168 billion ($1.3 billion) to this project, which is its largest single-sector investment in Kenya. The National Land Commission is currently working to identify beneficiaries, particularly where land is under communal ownership.
Entities
Isiolo-Mandera Highway · Kenya · National Land Commission · Qimiao Fan · World Bank