Consortium Zenith Construction Sdn. Bhd.
Featured in 1 tracked story · first seen
Situations
Penang Air Itam–Lim Chong Eu bypass project
2 clusters · 3 sources · last updated
Latest: Air Itam–Tun Dr Lim Chong Eu bypass project nears completion in Penang
The RM851 million Air Itam–Lim Chong Eu Expressway (LCE) bypass project in Penang has reached over 93 percent physical progress. The 5.7km route, designed to connect Bandar Ayer Itam and Farlim directly to the LCE, is ex