Bariloche municipal swimming pool construction
Overview
Construction of a municipal swimming pool in Playa Centenario, Bariloche, has progressed from foundational preparation to structural pouring.
Initially, work focused on preparing the foundations by applying a layer of H8 cleaning concrete to separate the natural ground from iron reinforcements. The project plan involved installing iron grids and formwork to pour H30 high-resistance concrete into 45-centimeter-high bases using a double 12-millimeter iron reinforcement structure.
Following these preparatory stages, the project reached a milestone with the commencement of concrete pouring for the bases, utilizing 31 cubic meters of H21 concrete to advance the structural foundations.
Entities
Timeline
-
[BUSINESS] 3 sourcesPlaya Centenario municipal pool begins concrete pouring for bases
Construction of the new municipal swimming pool in Playa Centenario, Bariloche, has begun pouring concrete for its structural bases.
-
[BUSINESS] 2 sourcesBariloche municipal swimming pool construction advances in Playa Centenario
Mayor Walter Cortés inspected the construction of the new Municipal Swimming Pool in Playa Centenario, Bariloche, as workers prepare the structural foundations.