China completes largest fusion magnet, plans 2027 ignition
Overview
In late July 2026, the Institute of Plasma Physics confirmed that the 582-ton, D-shaped toroidal-field magnet—21 m long, 12 m wide, and 3.3 m high—had passed acceptance testing after a six-year domestic development programme. The magnet stores about three times the energy of comparable ITER coils and is 1.3 times larger in volume. Built entirely with Chinese technology, it removes foreign supply dependence and will be installed in the upcoming BEST tokamak as part of the state-run CRAFT project, working with a high-temperature superconducting central solenoid to confine plasma above 100 million °C.
During the final test, the coil was driven to 60 kA, well above its nominal 46.5 kA design current, demonstrating a strong safety margin. Chinese officials say the achievement moves the target of generating electricity from a prototype “artificial Sun” reactor by around 2030 within reach. The programme plans its first ignition experiment by 2027 and envisions installing up to 16 such magnets to create a unified high-field system.
In August 2026, at the Fusion Energy Conference in Shanghai, officials identified controlled fusion as a priority for the nation’s upcoming ‘15th Five-Year Plan’. A consortium of nine enterprises, led by China Fusion Energy Co., Ltd., announced a joint mission to develop 25T high-temperature superconducting (HTS) magnets to support the China Circulation-4 project. This consortium aims to establish a dedicated production and testing line by 2028, with prototype magnet development targeted for 2030. The shift toward HTS technology is expected to allow for more compact fusion reactors and accelerate commercialization.
Entities
China · CRAFT project · International Thermonuclear Experimental Reactor (ITER) · Institute of Plasma Physics, Chinese Academy of Sciences · Chinese Academy of Sciences (CAS)
Claims
What the coverage asserts, and how many sources carry each claim.
- [● 4 SOURCES] China completed a 582‑tonne, 21 m × 12 m superconducting toroidal‑field magnet, the largest ever built.
- [● 4 SOURCES] The magnet stores about three times more energy than comparable ITER magnets.
- [● 4 SOURCES] The magnet is part of China’s CRAFT project and will be used in the upcoming BEST tokamak.
- [● 4 SOURCES] China aims to generate electricity from fusion by around 2030 using this technology.
- [● 4 SOURCES] The magnet was built entirely with domestic Chinese technology and materials, reducing foreign dependency.
- [● 4 SOURCES] The magnet passed acceptance testing after a six‑year development programme.
- [● 4 SOURCES] The magnet’s volume is about 1.3 times that of comparable ITER magnets.
- [● 4 SOURCES] The magnet can generate a magnetic field strong enough to confine plasma at temperatures exceeding 100 million °C.
Timeline
-
[TECHNOLOGY] 2 sourcesShanghai hosts fusion energy conference as nine firms target 2028 magnet milestone
At the 2026 Fusion Energy Conference in Shanghai, a nine-company consortium led by China Fusion Energy Co., Ltd. announced plans to develop 25T high-temperature superconducting magnets by 2028.
-
[TECHNOLOGY] 3 sourcesChina completes world's largest superconducting fusion magnet
China built and tested a 582‑ton, 21‑m superconducting magnet for fusion, surpassing ITER components and targeting ignition by 2027.
-
[TECHNOLOGY] 7 sourcesChina completes world’s largest superconducting fusion magnet
China has completed the world’s largest 582‑tonne superconducting fusion magnet, a key part of the CRAFT project and BEST tokamak, aiming to produce electricity from fusion by 2030.
-
[TECHNOLOGY] 2 sourcesChina advances fusion 'artificial sun' with key magnet test
China’s fusion program reported that two domestically built superconducting magnets cleared full‑load tests, moving the BEST reactor toward a 2027 completion and a 2030 electricity‑generation demo.
Sources
acvila30.ro · bedaromano.blog.ilsole24ore.com · breezyscroll.com · echo24.cz · eeo.com.cn · ithome.com · m.xataka.com · sapo.pt · sigmaearth.com · timesnowhindi.com · verohealthcenter.com · wor.com
This summary has been updated 4 times: see revision history