Monitor this situation.
Unsubscribe anytime.
[SITUATION] · [QUIET] · [BUSINESS]
2 clusters · 6 sources · 3 days · First seen · Last updated
Diyarbakır Airport ILS installation
Overview
Work to install an Instrument Landing System (ILS) at Diyarbakır Airport progressed toward completion in late October 2026. The project aimed to mitigate flight delays and diversions caused by low visibility and adverse weather, issues that had persisted because the backup runway lacked an ILS while the main runway underwent maintenance.
By early November, Minister of Transport and Infrastructure Abdulkadir Uraloğlu announced that infrastructure work and device assembly were finished. The system, installed on the parallel runway, entered the flight control and calibration phase, with flight checks scheduled to begin on November 2. The ILS will become officially operational once technical tests and international aviation standard verifications are completed.
Entities
Diyarbakır Airport · Ministry of Transport and Infrastructure · State Airports Authority · Abdulkadir Uraloğlu · Sezgin Tanrıkulu
Timeline
-
[BUSINESS] 2 sourcesDiyarbakır Airport installs new Instrument Landing System
A new Instrument Landing System (ILS) has been installed on the parallel runway at Diyarbakır Airport to maintain flight safety during main runway maintenance. Flight tests begin November 2.
-
[BUSINESS] 5 sourcesDiyarbakır Airport ILS installation nears completion
Installation of an Instrument Landing System at Diyarbakır Airport is nearing completion to resolve flight disruptions caused by poor weather and low visibility.
Sources
bursahakimiyet.com.tr · cumhuriyet.com.tr · gazetedamga.com.tr · karar.com · mucadelegazetesi.com.tr · tigrishaber.com