Spanish wind energy project legal challenges
Overview
Legal proceedings regarding large-scale wind energy developments in Spain have seen recent judicial support for renewable energy projects.
In Galicia, the High Court of Justice (TSXG) upheld wind farm developments in A Costa da Morte. The court dismissed an appeal from the environmental association Petón do Lobo concerning the Bustelo wind farm, ruling that neighboring wind farms sharing infrastructure do not constitute illegal project fragmentation. The court also denied a request to suspend authorizations for the Coto Muíño complex, citing insufficient evidence of irreparable harm.
In the Teruel regions, the Spanish Supreme Court dismissed an appeal against the environmental assessment for the Maestrazgo wind cluster, a project promoted by Copenhagen Infrastructure Partners involving 122 turbines. The court ruled that cited irregularities did not justify annulling the authorization or the environmental impact statement.
Following this, the Teruel Investigating Court found no irregularities in the administrative processing or environmental impact of the Maestrazgo project. While the court noted alleged arbitrariness and anomalies in other wind clusters and photovoltaic projects, it did not identify deficiencies regarding the Maestrazgo cluster. This follows a decision by the High Court of Justice of Madrid to reject requests to halt the project. Mayors from the Viento Alto Association stated that judicial warnings regarding irregularities applied only to unrelated projects, such as the Albarracín, L’Eliana, and Begués clusters, as well as the Masía I and Masía II photovoltaic plants.
Entities
Petón do Lobo · Copenhagen Infrastructure Partners · Teruel Investigating Court · Supreme Court of Spain · Teruel
Timeline
-
[BUSINESS] 2 sourcesMaestrazgo wind cluster project clears judicial review in Teruel
A Teruel court found no administrative or environmental irregularities in the Maestrazgo wind cluster project, referring the case to the National Court after previous attempts to halt it were rejected.
-
[BUSINESS] 4 sourcesSpanish Supreme Court approves Maestrazgo wind cluster project
Spain's Supreme Court has upheld the environmental authorization for the Maestrazgo wind cluster, a renewable energy project by CIP involving 122 turbines and a 1,000 million euro investment.
-
[BUSINESS] 3 sourcesGalician High Court upholds wind farm projects in A Costa da Morte
The High Court of Justice of Galicia has upheld the legality of the Bustelo and Coto Muíño wind farms, rejecting claims of project fragmentation and environmental evasion.