Ecuador incorporates 30 MW into national grid via Esmeraldas III project
The Ecuadorian government, through the Corporación Eléctrica del Ecuador (CELEC EP), has activated the third generation island of the Esmeraldas III thermoelectric project. This move incorporates 30 MW into the National Interconnected System (SNI) using 16 motors and their respective generators.
The operation follows the unilateral termination of a contract with Austral Technical Management (ATM) due to failures in the acquisition, installation, and maintenance of equipment. Government officials reported that the contractor had charged over USD 70 million for equipment that was reportedly broken or incompatible with the national grid.
Legal actions are underway to recover lost investments, including a criminal complaint for organized crime filed by CELEC, a report regarding potential embezzlement from the State Comptroller General, and an ongoing arbitration process in the Quito Chamber of Commerce. Authorities stated that the 30 MW currently being produced is expected to increase to 60 MW in the near future.