Ecuador implements industrial power cuts to manage energy crisis
Ecuador is navigating a critical energy period due to a severe dry season (estiaje) affecting hydroelectric reservoirs. President Daniel Noboa has assured the public that residential households will not face power outages, despite the low water levels in key reservoirs like Mazar. To preserve water levels and stabilize the national grid, the government has implemented a plan of continuous 48-hour power disconnections for approximately 9,089 high and medium voltage industrial companies.
To bolster the energy matrix, the government is leveraging the Toachi Pilatón complex, which contributes over 200 MW, and the Daule-Peripa plant. Additionally, two thermoelectric barges have been contracted to support the system. Looking ahead, new thermoelectric projects are expected to add 655 MW to the grid progressively by the first quarter of 2027.
In an effort to attract private investment and reduce costs for energy generation and storage, the government has eliminated VAT and the Outflow of Foreign Currency Tax (ISD) for the importation of necessary equipment. Furthermore, more than USD 3.5 million is being invested to modernize and expand the electrical infrastructure in the Cotopaxi province, benefiting over 120,000 residents.
Entities
CENACE · Cotopaxi · Cámara de Industrias y Producción · Daniel Noboa · ELEPCO · Ecuador · Government of Ecuador · Mazar · Mazar Reservoir · Toachi Pilatón · Toachi Pilatón
Claims
What the coverage asserts, and how many sources carry each claim.
- [● 2 SOURCES] The government implemented continuous 48-hour power disconnections for 9,089 high and medium voltage industrial companies. www.extra.ec · www.expreso.ec
- [○ 1 SOURCE] Industrial power cuts reduced national demand by approximately 300 MW, falling short of the 550 MW government target.
- [● 7 SOURCES] The Toachi Pilatón hydroelectric complex is contributing more than 200 MW to the national grid. imbaburaenlinea.com · cerolatitud.ec · fmmundo.com · radiocolosal.com · elmercurio.com.ec
- [● 2 SOURCES] The government is investing over USD 3.5 million to improve and expand electrical infrastructure in the Cotopaxi province. aldiaonline.net
- [● 4 SOURCES] The government eliminated VAT and the Outflow of Foreign Currency Tax (ISD) for importing equipment for private power generation and storage projects. www.expresatems.com · diariolosandes.com.ec · eluniverso.com
- [● 6 SOURCES] New thermoelectric projects are expected to add 655 MW to the system progressively by the first quarter of 2027. cerolatitud.ec · fmmundo.com · radiocolosal.com · elmercurio.com.ec
- [○ 1 SOURCE] Recent rains have led to a recovery in the water levels of the Mazar reservoir. www.larepublica.ec
- [● 8 SOURCES] President Daniel Noboa stated that Ecuadorian households will not experience power outages during the current dry season. imbaburaenlinea.com · cerolatitud.ec · fmmundo.com · elmercuriomanta.ec · radiocolosal.com · +1 more