The Long Thanh International Airport passenger terminal is transitioning from a construction site to a modern operational facility. Installation of essential aviation equipment is currently underway beneath the lotus-shaped roof structure.
Key installations include self-service bag drop counters, baggage conveyor systems, escalators, and elevators. Technical teams are currently testing and connecting various systems, including baggage handling equipment and passenger service modules. While some areas remain cordoned off for ongoing work, walkways, stone flooring, and railings are nearing completion.
As of early September 2026, the contract for the construction and installation of passenger terminal equipment (Package 5.10) has reached approximately 77.37% completion.