Vietnam Long Thanh Airport development

Overview

Vietnam continues to advance the Long Thanh International Airport project, targeting full commercial operation by late December 2026. Construction progress has accelerated, with essential works under component project 3 reaching approximately 86% completion. The passenger terminal is transitioning toward operational readiness through a “paperless journey” model, utilizing biometric technology, facial recognition, and a high-speed automated baggage handling system.

The Airports Corporation of Vietnam (ACV) has announced that the airport is projected to begin commercial operations at 0:00 on December 24, 2026. During this initial phase, the facility is expected to handle a maximum of 366 flights per week, comprising 322 domestic and 44 international flights. Major carriers, including Vietnam Airlines and Vietjet Air, are planning routes to connect the hub to Hanoi and other economic centers. Infrastructure testing is underway for the jet fuel supply system, which includes six storage tanks with a total capacity of 36,000 cubic meters.

To support passenger transit, authorities are focusing on road connectivity, such as the Ho Chi Minh City - Long Thanh - Dau Giay expressway, as rail links will not be operational during the early stages. To ensure these targets are met, the Ministry of Construction has issued directives for the ACV to submit operational plans by November 15, 2026. The Civil Aviation Authority of Vietnam is tasked with reviewing these plans by November 18 to facilitate a formal readiness review. Deputy Prime Minister Pham Gia Tuc has previously emphasized that relevant ministries and local authorities will be held accountable if delays occur.

Entities

Long Thanh International Airport · Airports Corporation of Vietnam · Pham Gia Túc · Civil Aviation Authority of Vietnam · Ho Chi Minh City

Claims

What the coverage asserts, and how many sources carry each claim.

Timeline

  1. [BUSINESS] 2 sources
    Vietnam Ministry of Construction sets deadlines for Long Thanh Airport preparation

    Vietnam's Ministry of Construction has set strict deadlines for ACV and the Civil Aviation Authority to finalize operational plans for the first phase of Long Thanh International Airport.

  2. [BUSINESS] 8 sources
    Long Thành International Airport faces project delays

    Six service projects at Long Thành International Airport face delays due to material shortages and logistics, prompting government directives to accelerate construction for a 2026 opening.

  3. [BUSINESS] 3 sources
    Long Thanh International Airport scheduled to begin operations in December 2026

    Long Thanh International Airport is set to begin operations on December 24, 2026, with an initial capacity of 366 weekly flights and a focus on developing critical road connectivity.

  4. [BUSINESS] 10 sources
    Long Thanh International Airport set to begin operations in December 2026

    Long Thanh International Airport is scheduled to begin commercial operations on December 24, 2026, initially handling up to 366 weekly flights including domestic and international routes.

  5. [BUSINESS] 3 sources
    Long Thanh Airport to implement paperless biometric travel

    Long Thanh Airport will launch with a paperless biometric system, using facial recognition and VNeID integration to streamline check-in, security, and boarding processes.

  6. [BUSINESS] 3 sources
    Long Thanh International Airport to undergo navigation system calibration

    Long Thanh International Airport will undergo navigation system and runway lighting calibration from October 11 to 19, 2026, as the project prepares for commercial operations.

  7. [BUSINESS] 2 sources
    Long Thanh International Airport advances toward trial operations

    Long Thanh International Airport enters trial operation preparation, featuring a complex 5,300-ton lotus-shaped roof lifted by 56 hydraulic jacks.

  8. [BUSINESS] 13 sources
    Long Thanh International Airport targets December 2026 commercial launch

    Long Thanh International Airport aims to begin commercial operations on December 24, 2026, with initial phases focusing on domestic and short-haul flights before reaching full capacity in late 2027.

  9. [BUSINESS] 5 sources
    Long Thanh International Airport sets passenger service fees

    Long Thanh International Airport will implement passenger service fees of 25 USD for international and 90,909 VND for domestic flights starting October 1, 2026.

  10. [BUSINESS] 4 sources
    Long Thanh International Airport terminal enters equipment installation phase

    The Long Thanh International Airport terminal is undergoing rapid equipment installation, with the passenger terminal construction package reaching over 77% completion as of September 2026.

  11. [BUSINESS] 2 sources
    Long Thanh International Airport construction enters final sprint

    Construction at Long Thanh International Airport is accelerating, with major packages like runways and fuel systems nearing 100% completion as the passenger terminal enters critical installation phases.

  12. [BUSINESS] 2 sources
    Dong Nai to auction hundreds of hectares for urban development

    Dong Nai authorities are planning auctions for hundreds of hectares of land to support urban and service development, including 90 hectares for the Long Thanh International Airport project.

  13. [BUSINESS] 3 sources
    Long Thanh International Airport construction reaches 80% output value

    Vietnam's major international airport project in Dong Nai has reached 80% output value, with over 7,100 workers currently constructing the high-tech passenger terminal.

  14. [BUSINESS] 9 sources
    Vietnam infrastructure projects accelerate construction during National Day holiday

    Vietnam's major infrastructure projects, including Long Thanh International Airport and Phu Cat Airport, are maintaining continuous construction through the National Day holiday to meet critical deadlines.

  15. [BUSINESS] 5 sources
    Long Thanh International Airport construction progress under strict oversight

    Vietnam's Civil Aviation Authority Director General has ordered strict oversight of Long Thanh International Airport's construction progress to prevent delays in the national key project.

  16. [BUSINESS] 2 sources
    Long Thanh International Airport draws interest from ANA and Korean Air

    Long Thanh Airport, set to open commercially in Dec 2026, was inspected by ANA and Korean Air, which are evaluating passenger and cargo services and see the hub as a key regional logistics centre.

  17. [BUSINESS] 2 sources
    Vietnam Airports Corp cuts 2,300 jobs as Long Thanh airport nears opening

    Vietnam Airports Corp cut over 2,300 staff, saving ~1.9 trn VND, while posting a 6,700 trn VND profit and keeping Long Thanh airport on track for a September trial and December commercial launch.

  18. [BUSINESS] 5 sources
    Long Thanh Airport in Vietnam prepares for test flights as terminal construction nears completion

    Long Thanh Airport’s passenger terminal is 80% complete, with key systems installed. ACV aims for test flights Sep‑Nov 2026 and commercial launch in Dec 2026, while VATM finalises flight‑operation systems.

  19. [BUSINESS] 2 sources
    Vietnam Airports Corp invests 39.5 trillion VND in Long Thanh Airport

    Vietnam Airports Corp (ACV) invested 39.5 trillion VND in Phase 1 of Long Thanh International Airport, accounting for 94 % of its unfinished assets, while reporting record Q2 profit and preparing Phase 2 to cap

  20. [BUSINESS] 2 sources
    Vietnam pushes urgent metro extension to Long Thanh International Airport

    Vietnam’s deputy prime minister approved an urgent 44.5 km metro extension from Ho Chi Minh City to Long Thanh Airport, to be built via PPP and completed by year‑end.

  21. [BUSINESS] 2 sources
    Vietnam expands airport capacity with Long Thanh International Airport project

    Vietnam pushes major airport upgrades, including the massive Long Thanh project for 100 million passengers, to boost trade, tourism and its regional aviation hub status.

Sources

baocalitoday.com · baogiaothong.vn · baolaocai.vn · baoxaydung.vn · biz.cafef.vn · cafebiz.vn · cafef.vn · doanhnghiephoinhap.vn · doanhnghieptiepthi.vn · dongnai.gov.vn · erzsebetter.hu · es.vietnamplus.vn · fr.vietnamplus.vn · htv.vn · kenh14.vn · kevesko.vn · kienthuc.net.vn · mekongasean.vn · nhandan.vn · phunuvietnam.vn · soha.vn · sputniknews.vn · thanhnien.vn · thelevisalazer.com · thoibaonganhang.vn · thuonghieusanpham.vn · thuysanvietnam.com.vn · tienphong.vn · tudonghoangaynay.vn · tuoitre.vn · vietnaminsider.vn · vietnamplus.vn · vir.com.vn · vtv.vn