Ontario Power Generation reports delays and cost increases for SMR project
Ontario Power Generation (OPG) has announced that its Darlington New Nuclear Project, featuring North America’s first commercial small modular reactor (SMR), is facing significant construction delays and budget overruns. The 300-megawatt unit, utilizing GE Vernova Hitachi’s BWRX-300 technology, is now unlikely to meet its scheduled October 2030 operational date.
Initial estimates for the project, which includes shared site infrastructure, were approximately 7.7 billion Canadian dollars (roughly 5.4 billion USD). OPG officials attributed the setbacks to ongoing engineering adjustments for the pioneering design and compounding supply chain disruptions. A comprehensive assessment to establish a new timeline and budget is expected to be substantially completed by mid-2027.
The project serves as a critical test case for SMR technology, which is being considered by developers in other regions, including Poland. While construction activities such as turbine building concrete work and tunnel boring preparations are underway, the delays pose a challenge to the momentum of the next-generation nuclear power movement.
Entities
Canada · Darlington · GE Vernova · GE Vernova Hitachi · Hitachi · Nicolle Butcher · Ontario Power Generation