Darlington small modular reactor project delays

Overview

Ontario Power Generation has announced that the Darlington New Nuclear Project, which features North America’s first small modular reactor (SMR), will miss its 2030 completion target and exceed its initial $7.7 billion Canadian budget.

Officials cited ongoing engineering adjustments, supply chain disruptions, inflation, and geopolitical risks as primary drivers for the setbacks. The 300-megawatt unit utilizes GE Vernova Hitachi technology. The utility is conducting a revised assessment of the project's cost and schedule, with results expected by mid-2027.

Despite these setbacks, the provincial government has awarded contracts worth approximately $66 million to eastern Ontario companies to support the build-out. These contracts, involving Gillam Construction Group and Mansteel Rebar, are expected to create roughly 200 jobs in the region. The project represents the first new nuclear construction in Canada in over three decades and serves as a critical test for SMR technology.

In a recent update, OPG noted that the delays specifically impact the October 2030 target for commercial operation. The utility attributed risks to the first-of-a-kind GE Vernova Hitachi BWRX-300 design. Conversely, OPG reported that the Pickering Generating Station refurbishment is currently ahead of schedule. Construction for those units is expected to begin in early 2027, pending approval from the Canadian Nuclear Safety Commission, with the goal of extending the station's service life by over 30 years.

As of November 2026, OPG confirmed that the project is unlikely to meet the October 2030 operational date. While construction activities, including tunnel boring preparations and concrete work for the turbine building, are currently underway, the delays present a challenge to the momentum of the next-generation nuclear power movement. The project remains a significant global test case for SMR technology, which is being considered by developers in other regions, such as Poland.

Entities

GE Vernova Hitachi · Ontario Power Generation · Hitachi · Mansteel Rebar · Nicolle Butcher

Timeline

  1. [BUSINESS] 6 sources
    Ontario Power Generation reports delays and cost increases for SMR project

    Ontario Power Generation reports that its pioneering small modular reactor project in Darlington will miss its 2030 operational target and exceed its 5.4 billion USD budget due to engineering and supply chained

  2. [BUSINESS] 4 sources
    Ontario Power Generation reports delays and cost overruns for Darlington SMR project

    Ontario Power Generation announced that its Darlington small modular reactor project will exceed its $7.7 billion budget and miss its 2030 operational target due to engineering and supply chain risks.