Stary Bidaczów bridge reconstruction underway

Construction is progressing on a new bridge over the Łada River in Stary Bidaczów, located on county road 2936L. The previous structure has been dismantled, and contractors are currently working on the foundations for the new crossing.

The project, valued at nearly 3 million PLN, aims to improve road safety and user comfort due to the poor technical condition of the original bridge. The investment includes comprehensive work on both the bridge structure and the adjacent section of the road.

Jan Małysza, a member of the County Board, noted that while the closure causes inconveniences for residents and drivers, the project is essential for traffic safety. A detour has been established through Nowy Bidaczów to accommodate travelers heading toward Wólka Biska, Biszcze, Potok Górny, and the Biszcza-Żary reservoir.

Entities

Biłgoraj County · Jan Małysza · Stary Bidaczów · Łada River