Tanzania upgrades rail infrastructure through MGR and SGR projects
Tanzania is implementing a dual strategy to enhance its railway network by upgrading the existing Meter Gauge Railway (MGR) and advancing the Standard Gauge Railway (SGR) construction.
To boost MGR capacity, the government is replacing steel sleepers with concrete sleepers. This initiative, supported by a 379 billion Tanzanian Shilling allocation for the Kaliua–Mpanda section, aims to increase annual cargo capacity from 500,000 tons to 18 million tons. A new factory is being established to produce concrete sleepers, which cost approximately $65 (130,000 TZS) each, compared to 360,000 TZS for steel versions. These concrete sleepers weigh 250 kg, significantly more than the current 39.7 kg sleepers, providing better stability for increased speeds.
Regarding the SGR, Minister for Transport Professor Makame Mbarawa inspected the Tabora–Kigoma section, which is estimated to cost $2.7 billion. Construction of the 460-metre-long Malagarasi Bridge is underway, a critical and complex component of the project. The Tabora–Kigoma section has reached 12 percent completion and is expected to be finished by 2029. Once operational, SGR trains are expected to reach speeds of 160 km/h, connecting Dar es Salaam to Kigoma and Mwanza by 2028.
Entities
Machibya Shiwa · Makame Mbarawa · Malagarasi Bridge · Tanzania · Tanzania Railways Corporation
Claims
What the coverage asserts, and how many sources carry each claim.
- [○ 1 SOURCE] MGR cargo capacity is projected to increase from 500,000 tons to 18 million tons per year through sleeper upgrades. fullshangweblog.co.tz
- [○ 1 SOURCE] The Tabora–Kigoma SGR section is estimated to cost $2.7 billion. dailynews.co.tz
- [○ 1 SOURCE] Concrete sleepers cost approximately $65 (130,000 TZS) compared to 360,000 TZS for steel sleepers. fullshangweblog.co.tz
- [○ 1 SOURCE] SGR services from Dar es Salaam to Mwanza are expected to begin in 2028. fullshangweblog.co.tz
- [● 2 SOURCES] The SGR project is expected to be completed by 2029. www.michuzi.co.tz · dailynews.co.tz
- [● 2 SOURCES] SGR trains are expected to reach speeds of 160 km/h. www.michuzi.co.tz · dailynews.co.tz
- [● 2 SOURCES] The Tabora–Kigoma SGR project has reached 12 percent completion. www.michuzi.co.tz · dailynews.co.tz
- [○ 1 SOURCE] The government allocated 379 billion Tanzanian Shillings to improve the Kaliua–Mpanda MGR section. fullshangweblog.co.tz