Ben Thanh - Suoi Tien metro extension designated as urgent project
The Vietnamese Government has officially designated the extension of the Ben Thanh - Suoi Tien metro line to the Dong Nai administrative center and Long Thanh International Airport as an urgent construction project via Resolution No. 255/NQ-CP.
The project spans approximately 44.5 km and is divided into two segments: a 7.1 km section from Suoi Tien station to the Dong Nai administrative center, and a 36.4 km section connecting to Long Thanh International Airport. The line is designed for a maximum speed of 120 km/h.
The Dong Nai People's Committee has been tasked with leading the project's implementation under the 2025 Construction Law, focusing on public-private partnership (PPP) regulations, land clearance, and ensuring social stability during compensation processes. Land clearance is projected to be completed by the end of 2026. The Ministry of Finance will oversee project supervision, while the Ministry of Construction will provide technical guidance to ensure safety and quality standards.
Entities
Ben Thanh - Suoi Tien Metro Line · Dai Quang Minh Real Estate Investment JSC · Dong Nai People's Committee · Dong Nai Province · Government of Vietnam · Long Thanh International Airport · Ministry of Construction · Ministry of Finance · Na San Airport
Claims
What the coverage asserts, and how many sources carry each claim.
- [○ 1 SOURCE] The first segment of the metro extension, from Suoi Tien station to the Dong Nai City Administrative Center, is about 7.1 km long. phunuvietnam.vn
- [○ 1 SOURCE] The Ministry of Construction is collecting opinions on the detailed planning dossier for Na San Airport in Son La province. soha.vn
- [○ 1 SOURCE] Land clearance for the 25B road project through Long Thanh Ward has reached 100% completion.
- [○ 1 SOURCE] The 25B road project will be 80 meters wide and will enhance connectivity to National Highway 51 and Long Thanh International Airport.
- [● 2 SOURCES] The metro extension project to Long Thanh Airport will have a length of approximately 44.5 km. phunuvietnam.vn · tuoitre.vn
- [● 6 SOURCES] The Government has assigned the Dong Nai People's Committee to implement the extension of the Ben Thanh - Suoi Tien metro line. phunuvietnam.vn · baoxaydung.vn · cafef.vn · tienphong.vn · tuoitre.vn · +1 more
- [○ 1 SOURCE] The planned total area for Na San Airport is over 544 hectares. soha.vn
- [○ 1 SOURCE] Na San Airport is planned to meet ICAO 4C technical standards. soha.vn
- [● 6 SOURCES] The Ministry of Construction will provide support and guidance to the Dong Nai People's Committee regarding construction regulations. phunuvietnam.vn · cafef.vn · tienphong.vn · vtv.vn · baoxaydung.vn
- [● 4 SOURCES] The metro line has a maximum design speed of 120 km/h. phunuvietnam.vn · cafef.vn · tienphong.vn · tuoitre.vn
- [● 2 SOURCES] The project consists of two segments: segment 1 is 7.1 km long, and segment 2 is 36.4 km long. tuoitre.vn · phunuvietnam.vn
- [● 7 SOURCES] The Government issued Resolution No. 255/NQ-CP to classify the Ben Thanh - Suoi Tien metro extension as an urgent construction project. phunuvietnam.vn · cafef.vn · tienphong.vn · tuoitre.vn · vtv.vn · +1 more