Cahora Bassa hydroelectric water management
Overview
Hidroeléctrica de Cahora Bassa (HCB) has reported a recovery in water resources and power production following a two-year drought. During the first half of 2026, the company generated 6,399.03 gigawatt-hours, a 13% increase from the previous year, while reservoir storage levels rose from a low of 20% in January to 56% by the end of June.
In September 2026, as part of an annual maintenance programme and following the shutdown of the Songo Substation, HCB scheduled the opening of a mid-depth spillway at 80% capacity. On 20 September, the company conducted this ‘one-off, controlled and technically approved’ maneuver to ensure the continuity of flow along the Zambezi River and meet ecological water requirements. The operation considered hydrological and climatic forecasts, including El Niño scenarios, to support riverbank communities and preserve ecosystem balance ahead of the rainy season.
In late October 2026, HCB announced the postponement of its Extraordinary General Meeting, which had been originally scheduled for 16 October. The company did not disclose the reasons for the delay, and a new date has not yet been set.
Entities
Hidroeléctrica de Cahora Bassa · Mozambique · Zambezi Basin · Songo Substation · Zambezi River
Timeline
-
[BUSINESS] 2 sourcesHidroeléctrica de Cahora Bassa postpones extraordinary general meeting
Hidroeléctrica de Cahora Bassa has postponed its Extraordinary General Meeting scheduled for October 16, 2026, while reporting a 13% increase in energy production for the first half of the year.
-
[BUSINESS] 2 sourcesHidroeléctrica de Cahora Bassa increases power output and reservoir levels
Hidroeléctrica de Cahora Bassa increased power generation by 13% in H1 2026 while simultaneously recovering reservoir storage levels from a historic low to 56% following a severe drought.
-
[BUSINESS] 2 sourcesHidroeléctrica de Cahora Bassa to open Zambezi spillway at 80% capacity
Hidroeléctrica de Cahora Bassa will open a spillway at 80% capacity on 20 September to maintain the Zambezi River's ecological flow during maintenance and substation shutdowns.