Oven Mountain Pumped Hydro project cancellation
Overview
Alinta Energy has cancelled the $1.8 billion Oven Mountain Pumped Hydro Scheme in northern New South Wales. The 900MW project, located in the Armidale Renewable Energy Zone (REZ), was intended to provide 7,200MWh of energy storage to power over 600,000 homes.
The company cited economic and timing challenges as the reasons for the decision, specifically highlighting the absence of a critical transmission line upgrade necessary for project viability. While the project required only a 15km connection to the existing Line 965 between Armidale and Kempsey, delays in infrastructure upgrades and connection decisions by EnergyCo reportedly contributed to the cancellation.
Despite being at an advanced development stage and having received $9.64 million in grants from the NSW government, the project was deemed unviable. Local officials, including Oxley MP Michael Kemp, described the cancellation as a “devastating loss” for the regional economy, specifically for the Macleay Valley, noting the potential loss of hundreds of jobs for local contractors and tradespeople in the Armidale and Kempsey areas.
Parallel developments in the New England REZ involve an environmental impact statement (EIS) for transmission lines. The EIS indicates that the village of Rouchel in the Upper Hunter will face the highest visual impact, specifically noting four high visual impact ratings near Rouchel Brook that affect the Rouchel Uniting Church. While EnergyCo stated the project area maximizes distance to dwellings, residents have requested the corridor be moved further west to protect homes and community landmarks.
Entities
Oven Mountain Pumped Hydro · EnergyCo · Alinta Energy · New England Renewable Energy Zone · New York Power Authority
Timeline
-
[BUSINESS] 4 sourcesAlinta Energy cancels $1.8 billion Oven Mountain pumped hydro project
Alinta Energy has scrapped the $1.8 billion Oven Mountain Pumped Hydro project in NSW, citing transmission line delays and economic challenges, resulting in a significant loss of projected regional jobs.
-
[BUSINESS] 2 sourcesNew England Renewable Energy Zone projects face setbacks
Alinta Energy has scrapped the Oven Mountain Pumped Hydro project due to economic challenges, while an EIS reveals the village of Rouchel will face the highest visual impact from REZ transmission lines.
-
[BUSINESS] 3 sourcesRenewable energy projects face setbacks in Australia and New York
Major renewable energy initiatives face hurdles as Australia's Oven Mountain Pumped Hydro project is scrapped and New York rescinds a key permit for the Propel NY Energy project.
Sources
armidaleexpress.com.au · esdnews.com.au · gleninnesexaminer.com.au · inverelltimes.com.au · nctimes.com.au · netimes.com.au · newsday.com · theland.com.au
This summary has been updated 2 times: see revision history