Romania motorway projects reach key milestones on A1 and A3
Major infrastructure projects across Romania's motorway network are reaching critical milestones. On the A1 motorway, the Margina-Holdea section has achieved a significant breakthrough with the completion of excavation for the country's longest highway tunnels. These tunnels, featuring galleries of 1,985 and 1,825 meters, are part of a project aimed at ensuring continuous high-speed travel between Boița and Nădlac, with full completion expected by mid-2027.
On the A3 Transylvania Motorway, the Suplacu de Barcău-Chiribiș section is nearing completion, with experts from Pro Infrastructură estimating an opening in November. While asphalt has been laid across most of the 26.35-kilometer stretch, some work remains near the Suplacu de Barcău viaduct. Additionally, the section between Zimbor and Nădășelu is expected to be ready for traffic by December, following significant progress by contractors UMB and Ozaltin.
In the Sibiu-Pitești motorway project, Section 4 between Tigveni and Curtea de Argeș has reached 99% physical completion. Current efforts are focused on safety system testing within the 1,350-meter Momaia tunnel, with the section potentially opening in 2026, ahead of the February 2027 contractual deadline.
Entities
A3 motorway · A7 motorway · Asociația Pro Infrastructură · Autostrada Transilvania · CNAIR · Erbașu · Ozaltin · Pro Infrastructură · Romania · Spedition UMB · UMB
Claims
What the coverage asserts, and how many sources carry each claim.
- [○ 1 SOURCE] The long tunnel consists of two galleries measuring 1,825 meters and 1,985 meters. adevarul.ro
- [○ 1 SOURCE] Forty-eight beams have been installed on the first six openings of the main passage. www.ziuadevest.ro
- [○ 1 SOURCE] The Margina viaduct, measuring 350 meters, has completed its beam installation phase with 64 beams. www.ziuadevest.ro
- [○ 1 SOURCE] Beam installation has begun on the 1,085-meter passage crossing the Lugoj–Ilia railway. www.ziuadevest.ro
- [○ 1 SOURCE] The project includes an on-site beam factory and an asphalt station. www.ziuadevest.ro
- [○ 1 SOURCE] Excavation of the four tunnel galleries on the A1 Margina–Holdea section has been completed. adevarul.ro