Romania transport projects – End July 2026
81 clusters · 173 sources · last updated
Latest: Romania secures €630 million EU loan for Brașov‑Sighișoara rail upgrade
Late July 2026 brought further advances across Romania’s transport network. On the A1 motorway, work on the missing Margina–Holdea segment accelerated. Tunnel 1 is over 90 % complete, while Tunnel 2 awaits excavation of
Romanian highway construction progress
2 clusters · 9 sources · last updated
Latest: Romania advances construction of highest viaduct on A1 Sibiu‑Pitești
In late July 2026 Romania reported significant advances on two major highway projects. On July 22 the Turkish contractor Makyol was working on the 68‑km A13 Sibiu‑Făgăraș route, with sections 1 and 2 at roughly 17 % and