Romanian Ministry of Transport
Featured in 3 tracked stories · first seen
Situations
Romania transport infrastructure upgrades
2 clusters · 8 sources · last updated
Latest: Romania begins rehabilitation of eight tunnels on Bumbești–Livezeni railway line
In early August 2026 Romania reported progress on several major transport projects. The Bucharest tram line Lot 6, a 5.3‑km stretch serving lines 16 and 36, had moved beyond 90 % excavation, with work shifting to support
Romania transport projects – Late July 2026
81 clusters · 172 sources · last updated
Latest: Romania secures €630 million EU loan for Brașov‑Sighișoara rail upgrade
By the end of July 2026 the A1 motorway’s missing Margina–Holdea segment is nearing completion. Tunnel 1’s two galleries are over 90 % finished, while Tunnel 2 still requires excavation of about 270 m on the UMB‑executed
Also covered in
-
Romania launches first PESA electric regional trains
[TECHNOLOGY] · 6 sources ·